Sometime between 2003 and 2004, Plymouth maintenance staff built a boardwalk across the south end of Lake Camelot out of street signposts, rope and wood. They didn't get a permit from the Minnesota Department of Natural Resources. The crossing lasted about twenty years. Crews started taking it out on January 13, 2026, and the removal continued into February.
If you walk the lake from Cheshire Parkway or come in off Chankahda Trail, you've probably seen the result of a 2025 state ruling. Lake Camelot gave up a close-to-the-water crossing. In return it is getting a layout the city can keep open after the snow falls. The south boardwalk had to go before the rest of the plan could work.
A crossing nobody planned to keep
The city's own documents are frank about the old boardwalk. Its eastern approach didn't meet slope requirements under the Americans with Disabilities Act. The city also described it as "deteriorating beyond its useful life."
By the time the city asked to replace it, the boardwalk was no longer the only way around the south end. In 2018 Plymouth put in an asphalt trail around the south side of the lake. That trail links the Camelot 9 at Begin Oaks neighborhood with the parking lot trailhead on the southwest side of the lake. The trail's existence decided the boardwalk's fate.
The application listed two alternatives. One was to build nothing. The other was to replace the boardwalk with docks on the shoreline. The city rejected both and asked to rebuild the boardwalk so people could keep crossing the water as before, instead of using the asphalt trail.
The state said no, partly based on the city's own plan
The DNR issued its Findings of Fact on January 29, 2025, and denied the permit. The decision is worth reading in full. The DNR findings posted by the City of Plymouth contain the central finding:
"The project application does not demonstrate that the boardwalk reconstruction is the minimal impact solution to a specific need."
The agency did not find that the boardwalk was dangerous. It said the structure had stood on the wetland fringe for 20 years with no reports of blocked navigation or water safety hazards. It also described the lake as a shallow public water wetland that is not significant fish and wildlife habitat. The test the boardwalk failed was need. The DNR wrote that replacing it "is not necessary for local residents to connect with wildlife or to circumnavigate the lake," because the paved trail already handled both.
The physical impact counted against it too. The application estimated an excavation 500 square feet by 3 feet deep, about 55 cubic yards, at each abutment. The DNR said the final design could add impacts that weren't yet known. It called the dock alternative the "minimum encroachment alternative."
On November 26, 2024, the Plymouth City Council adopted a Lake Camelot Park Master Plan. That plan showed the boardwalk removed and replaced with fishing pier docks. The DNR cited that plan to find the replacement request inconsistent with local land management plans. The application was routed for a 30-day comment period starting November 18, 2024, and no comments came in. The DNR also noted that no city programs used the boardwalk.
What was built instead
Once the south crossing was off the table, the renovation moved to the north, east and west edges of the park. Crews started removing the south boardwalk on January 13, 2026. South dock installation was scheduled to begin February 4. Most of the other work followed through spring and summer.
| Piece | Where it sits | Latest city status |
|---|---|---|
| South fishing docks | Former south boardwalk location | Installation scheduled from Feb. 4, 2026; paving by the two docks planned in early September |
| East boardwalk | East side of the lake | Built, with concrete approaches poured, as of Sept. 3, 2026 |
| North boardwalk | Chankahda Trail edge | Drivable design built with Chankahda Trail Phase 3; under construction as of Feb. 2, 2026 |
| Castle-themed playground | North side of the park | Installation began in September; about 4 to 6 weeks including poured-in-place surfacing |
| Four-season restroom | Cheshire Parkway, west side | Nearing completion; opens after a certificate of occupancy |
The playground went in with its biggest pieces first. The city's September 3 update says installation began with the castle, and a crane set the three tallest features. The master plan lays out separate play zones for ages 2 to 5 and 5 to 12. The same update says the trail between the north and east boardwalks had been reclaimed and was scheduled for paving that week.
The new layout sets up a winter loop
The city's explainer on the boardwalk decision describes the benefit. The north boardwalk is being replaced with a drivable structure as part of Chankahda Trail Phase 3. It will make the trail along Chankahda continuous and tie into the park's existing paths. The explainer says that, from preliminary discussions, the DNR saw this boardwalk as meeting its criteria because there is no alternative location and it sits as close to the shoreline as possible.
The explainer then says that with the drivable north boardwalk and the replacement of the small bridge on the east side, "maintenance staff will be able to plow a continuous loop around Lake Camelot during the winter."
The old signpost crossing could not support that loop. Rope and wood can't carry a plow, and the eastern approach didn't meet ADA slope standards. The new pieces were designed with winter maintenance in mind. The loop also uses the paved 2018 south trail that the DNR pointed to as a reason the old boardwalk wasn't needed.
Some details aren't settled yet. Citywide, Plymouth says snow removal is approved for about 123 of its roughly 186 trail miles, subject to available resources. The city's documents describe the plowed Lake Camelot loop as the goal of the design. We haven't found a posted route confirming it for this winter. The restroom on Cheshire Parkway is called a "four-season restroom" in the project materials. The city has not posted winter hours for it.
Dates between now and November
Two separate projects come together at Lake Camelot this fall, and both have dates in the next several weeks.
- October 15, 2026. This is the city's target for substantial completion of the park renovation. The latest posted update is from September 3. At that point the playground was mid-installation and the restroom was waiting on final inspection, so check the city's park and trail projects page before you plan a playground visit.
- Parking. The north parking lot was closed in April and was to stay closed through the end of construction. The Cheshire Parking Lot at 5724 Cheshire Parkway reopened in June, then closed again for utility work in late July. The city hasn't posted a later update on either lot.
- November 2026. Chankahda Trail is still closed between Cheshire Parkway and Yucca Lane. The city expects that stretch, along with the south leg of Yucca Lane, to reopen in November. As of the city's October 8 construction update, crews were installing storm sewer and building a retaining wall. Grading and gravel base prep for curb and gutter were planned for the following week.
Phase 3 runs from Cheshire Parkway to Northwest Boulevard. It finishes the corridor rebuild that the Sun Sailor described as starting with Highway 101 to Peony Lane, then Peony Lane to Vicksburg Lane. When the road reopens, the north boardwalk becomes the link between the rebuilt Chankahda trail and the paths around the lake.
If you want to read the reasoning yourself, the city has posted the master plan and its boardwalk explainer next to the DNR findings. Together they explain why the south crossing was removed and how the plowed loop is supposed to work. Questions about the project go to Plymouth Parks & Recreation at 763-509-5940.
Projects like the Lake Camelot renovation and the Chankahda Trail rebuild change how a part of Plymouth works day to day, and The Steadman Team follows them parcel by parcel. If you own property near Lake Camelot or the Chankahda corridor and want to know how this work fits into your plans, request a private consultation and valuation.